Covers Lessons 4โ6: Gantt charts, resource allocation, dummy activities, multiple critical paths, cost-time trade-offs, and mixed project problems.
Multiple Choice
Question set not yet written, use the module quiz for now
Its question set has not been written, so there is nothing here to attempt. Nothing you have done is lost, and the lessons either side of it are unaffected.
To test yourself on this material now, use the module quiz, which covers the same content.
Short Answer
1. A project has: A(3,-), B(4,A), C(2,A), D(5,B), E(5,C), F(2,D,E). (a) Find all critical paths. (b) If D's duration increases to 6, what happens? (c) Draw a Gantt chart showing both paths. (d) Crash D by 1 ($\$500$) and E by 1 ($\$400$). New duration and cost? 5 MARKS
2. (a) Explain why a Gantt chart is better than an AOA network for presenting a project schedule to a client. (b) A project has two critical paths that share no activities. You have a budget to crash one activity on each path by 1 day. A shared start activity could be crashed by 1 day for the same cost as two separate crashes. Why is the shared crash better? (c) What is the difference between a lag and a lead? 3 MARKS
Q1 (5 marks): (a) Path correct [1]. (b) Effect [1]. (c) Gantt [1.5]. (d) Cost [1.5].
Q2 (3 marks): (a) Explanation [1]. (b) Reason [1]. (c) Difference [1].
Tick when you have finished all questions and checked your answers.