Year 12 Maths Standard Checkpoint 2 ~25 min

Checkpoint 2: Advanced Scheduling

Covers Lessons 4โ€“6: Gantt charts, resource allocation, dummy activities, multiple critical paths, cost-time trade-offs, and mixed project problems.

๐Ÿ
Know

Key Facts

  • Gantt chart conventions
  • Multiple critical paths
  • Crash cost slopes
Understand

Concepts

  • Resource levelling
  • Lags and leads
  • Optimal duration
Can Do

Skills

  • Draw Gantt charts
  • Analyse multiple paths
  • Solve mixed problems

Multiple Choice

MC

Revision Multiple Choice

Question set not yet written, use the module quiz for now

This checkpoint is not available yet.

Its question set has not been written, so there is nothing here to attempt. Nothing you have done is lost, and the lessons either side of it are unaffected.

To test yourself on this material now, use the module quiz, which covers the same content.

Short Answer

๐Ÿ“

Extended Questions

ApplyBand 4

1. A project has: A(3,-), B(4,A), C(2,A), D(5,B), E(5,C), F(2,D,E). (a) Find all critical paths. (b) If D's duration increases to 6, what happens? (c) Draw a Gantt chart showing both paths. (d) Crash D by 1 ($\$500$) and E by 1 ($\$400$). New duration and cost? 5 MARKS

Answer in your workbook
AnalyseBand 5

2. (a) Explain why a Gantt chart is better than an AOA network for presenting a project schedule to a client. (b) A project has two critical paths that share no activities. You have a budget to crash one activity on each path by 1 day. A shared start activity could be crashed by 1 day for the same cost as two separate crashes. Why is the shared crash better? (c) What is the difference between a lag and a lead? 3 MARKS

Answer in your workbook

Comprehensive Answers

โ–ผ

Short Answer Model Answers

Q1 (5 marks): (a) Path correct [1]. (b) Effect [1]. (c) Gantt [1.5]. (d) Cost [1.5].

Q2 (3 marks): (a) Explanation [1]. (b) Reason [1]. (c) Difference [1].